 |
Civilian
Aviation (Lear Jet)

There was a very tight time schedule with unusual conditions
associated with the Lear Jet project. Management had
observed the successes of other aircraft manufacturers
who had used Megadoor and wanted to experience the same
success. The project includes 6 finishing and paint
bays and 1 delivery bay.
|

|

The Megadoor design experts were called in very early
to consult with the conceptual design of this new facility.
An important part of the criteria of the building design
centered around the turning over of each newly manufactured
aircraft to its new owner. This design team worked together
to create an exceptionally efficient and attractive
facility. The Megadoors were delivered and installed
as needed to meet the timing of the owners, and Lear
Jet was quite pleased. In the delivery process of turning
a new aircraft over to a customer, the delivery bay
door has become an integral part of the delivery process.

|

|
 |
| Civilian
Aviation (Bombardier)

Although the structure was well under way, because of
an already established relationship with the internal
design/build team, the Megadoor professionals were invited
to become involved and meet the individual responsible
for the new facility. Because the project had been under
construction before the meeting with Megadoor, time
was of the essence.
|
 |
| 
The initial meeting with Bombardier resulted in a sharing
of ideas, including eight different options presented
by Megadoors design architect. Megadoor understood
the scope of the project and was committed to making
certain the owner received what was expected. The Megadoor
cost effective solution tailored the doors to the manufacturers
specific needs and construction schedule by marrying
the production capabilities to the construction requirements

|
 |
| Civilian
Aviation
(Boeing Wichita, Kansas)

As part of a new strategy, Boeing began a program of
converting passenger aircraft to cargo aircraft. This
production effort required that the entire aircraft
be disassembled, a procedure which had to be conducted
in a totally enclosed structure. The only spot on which
this structure could be built was on a ground slope
of about four feet. Additionally, every bay of the structure
had to have total access, along with other specific
engineering criteria. And, to further complicate matters,
the project had to be executed in a very cost effective
manner and had to be completed within very unusual time
constraints.
|
 |
| 
Megadoors design architect assisted the Boeing
architects in developing a very unique structure that
would accommodate all the criteria set forth in the
initial plan, and would marry the Megadoors to the structure.
The entire facility was redesigned to work with the
slope of the terrain and to eliminate the need for space
consuming pockets needed for sliding doors. Megadoor
worked diligently to maintain aesthetic appeal and continuity,
and was able to customize the unique Megadoor swing-a-way
vertical mullions in order to provide complete
access to every bay. In addition, the Megadoor installation
professionals were there throughout the installation
process to ensure proper installation and function of
the doors. The result is a very attractive, cost effective
installation completed within the tim frame desired.

|
 |
 |
| Military
Aviation (New York ANG)

This unusual project required the alteration of an existing
hangar and a new facility for the fuel systems/corrosion
control operation. And, the final product was not to
look like an "added to" facility.
|
 |
| 
The Megadoor solution saved over 3000 sq. ft. of scope
area that could be better utilized in the shop areas.
By making both Hangar doors exactly the same, it simplified
the design. Megadoors design architect worked
hand in hand with the architectural firm Burns & McDonnell,
selected by the New York ANG to change the design concept
to a Megadoor approach to the problem. The new structure
had originally been designed around sliding doors.

|
 |
| Military
Aviation (Shaped Hangar for B-1)

Housing the innovative B-1 Bomber requires an innovative
facility. That is exactly what the Kansas Air National
Guard needed in Wichita, and even though the Unit officials
had seen other Megadoor shaped hangar designs, the maintenance
people needed to be convinced.
|
 |
| 
The way to demonstrate how Megadoors approach
to aircraft hangar design works was to view an existing
installation. Therefore, the entire Kansas design team
together with the aircraft maintenance team went to
Memphis to review another facility and study the shaped
hangar concept. Once everyone was convinced this was
the approach for the Kansas ANG, the Megadoor design
professionals worked with the ANGs architect to
incorporate many other good design points and to maximize
the shaped hangar design. The handsome facility is completely
and efficiently operational and proved again the advantages
of "form following function."

|
 |
 |
| Military
Aviation (Connecticut Army Aviation)

The unique and challenging aspect of this project for
the Connecticut Army Aviation was to retrofit an old,
existing hangar and to build an adjacent entirely new
hangar, all within a very tight time frame.
|
 |
| 
Based largely on the outstanding reputation Megadoor
has earned throughout the Military community, Megadoors
design architect was invited to consult with the Connecticut
Army Aviation on this unusual project. At a job site
meeting, a design began to be formulated which included
building an entirely new truss system to marry the old
building to the new structure. A 130 Megadoor
was installed on the existing structure, and a 140
Megadoor on the new hangar. The installation of the
attractive Megadoors made the facility look totally
new and the low maintenance Megadoors helped modernize
and streamline the entire base.

|
 |
| Military
Aviation (USCG Atlantic City)

The United States Coast Guard wanted to get six Dolphin
Aerospatiale HH 65A helicopters comfortably into one
hangar without any one of them being behind another.
The facility would function in five distinct areas
those being aircraft hangar, maintenance shops, berthing,
administration and storage. The Coast Guards architects
were about to design the structure with a traditional,
rectangular approach when the Megadoor problem solving
team was invited to participate.
|
 |
| 
Megadoors design architect began to work very
closely with the Coast Guards chosen architects
to explore other creative, non-traditional solutions
to the helicopter hangar problem. The entire design
team began to think outside the box and the results
were astounding. The new design became an L-shaped hangar
with the central control point of the facility in the
corner of the L. Because of the flexibility of the Megadoor,
each leg of the L accommodated three helicopters, any
one of which can enter or leave at any time - with none
of them behind another. The Megadoor design fit the
unusual mission requirements of the Coast Guard, and
the vertical lift Megadoors
proved to fit the need far better than sliding doors.
The building meets all the requirements of the Coast
Guards quality shore facility, including ease
of construction, functionality, flexibility, safety,
maintainability, cost effectiveness, project expansion,
aesthetics and the creation of an environment which
allows a source of pride for the USCG, as well as a
prototype for future Coast Guard facilities.

|
 |
| Megadoor
Teams with Summit Structures at Patuxant Naval Air Station
Megadoor,
Inc., a local manufacturer of aluminum reinforced, up-ward
acting, reinforced fabric doors, announces the completion
of the V-22 Osprey hangar at the Patuxant Naval Air
Station in Maryland. The new installation will provide
the Department of the Navy a base for the Osprey program’s
continued research and development. |
 |
| Megadoor,
together with general contractors J.A. Jone's Construction,
McGrath Construction and Summit Structures, Inc., agreed
to complete this project within an aggressive 60-day
time frame. The design of the project and delivery of
materials was completed in six weeks and installation
was executed without interruption to routine base proceedings.
The
Megadoor 1500 series doors provide unimpeded movement
of the Osprey with a clear opening measuring 100’
wide by 33’ high. The aluminum reinforced, fabric
doors require no stacking area within the building area
or within the opening. Massive extruded aluminum intermediate
beams allow the door to be designed for virtually any
wind loading condition. Additionally, the doors are
fabricated in strict compliance with military specifications
as well as regional building codes, and the PVC coated,
polyester door fabric has been UV stabilized for long
life.
The
versatility of the Megadoor has made the door a favored
selection of many architectural and engineering firms
involved in aviation facilities. Megadoor installations
can be found in all facets of the aviation industry,
including military, commercial, private and aircraft
manufacturing facilities across the continental United
States, Canada and Alaska.
The
unique Megadoor can be designed to accommodate virtually
any application, and the Megadoor team of professionals
is available to provide design assistance and pertinent
details to the design professional.

|
 |
|
RAF Valley - Refurbishment
of Gaydon Hangar
Like many bases within the UK, the existing hangar doors
were old and difficult to operate. They were opened
by a hand wheel attached to the door leaf at low level.
It took a long time to open them and consequently they
stayed open for long periods of time. The doors were
also larger than was required for modern aircraft; this
resulted in heat loss and a less than perfect working
environment for the aircraft technicians.
|
 |

The entire end of the building was reclad, together with
translucent panels at high level. The existing centre
door leafs were removed and a 22m wide x 7m high electrically
operated Megadoor was installed. This was split in two,
10m one side and 12m the other, separated by a swing-up
column, which enables the full width of 22m to be achieved
when required. For most of the aircraft, it is sufficient
to open up only one side, thus reducing heat loss and
maintaining an improved working environment. |
 |
| Steel
Mills (Pot Room Doors)

Over the years, management of this mini-mill in Northwest
Indiana was faced with almost constant maintenance,
and the all too frequent need to replace the large door
leading into their pot room. Failure of the traditional
doors being used at the time was due to the extreme
size of the opening and the dusty, hot environment in
which this door operates. Management was also concerned
about any disruption to the movement of heavy equipment
in and out of the pot room resulting from door failure.
|
 |
| 
Since the original had been installed, several other
door products were tried but none could withstand the
harsh conditions without considerable maintenance and
occasional downtime. They were simply not able to get
the reliability they wanted from any door they tried.
That is, until a MEGADOOR was installed. Management
has since found the MEGADOOR really is specifically
designed to withstand the most extreme environments
- including those in a steel mill pot room.

|
 |
| Steel
Industry (Macsteel)
Existing
rolling steel exterior doors were a source of major
and costly maintenance problems. The rolling rubber
and rolling steel doors often failed to perform and
provided little seal or insulation value, especially
during high winds where they also proved difficult to
operate.
|
 |
| 
The MEGADOOR is engineered to perform in high windloads
and is reliable in dirty and dusty environments like
steel mills. The users at Macsteel require frequent
cycles in their demanding facility but have the comfort
of knowing their new doors will operate properly, even
in the windiest conditions. They also have the comfort
provided by the great insulating value of the MEGADOOR
and no more worries about air infiltration because the
seal only improves as the windload increases.

|
 |
| Shaped
Hangar Design with Megadoor |
In
2004 Megadoor supplied two multiple doors to Qantas
Airlines for their new maintenance hangars at Sydney
Airport in Australia. With Megadoor it was possible
to design an innovative facility shaped around the aircraft.
Each
multiple door is divided into 5 door leaves with swing-up
mullions between. With this solution, the flexibility
of the hangar door opening is optimal. The size of the
ope92x22/10 m (width x height max/min). |
 |
 |
Ship
Yards (Trinity Yachts)

Trinity Yachts in New Orleans, LA., a major manufacturer
of luxury yachts and boats, needed to increase production
at their facility by performing the finishing task in
a controlled environment. By adding large doors to an
existing three-bay building, the interior could be heated
for proper finishing and ventilated as needed. The yachts
could then be removed by large cranes upon completion.
|
 |

Several door manufacturers were contacted but only MEGADOOR
could meet the criteria of Trinity Yachts. The doors
had to cover the entire opening width and height, withstand
the corrosiveness of the sea air, protect the interior
from inclement weather, allow workers to control the
environment inside the facility by using door position,
and install within a confined building area. MEGADOOR
engineers provided the general contractor and building
manufacturer with the necessary design assistance and
installed the door within the timeframe requested by
the owner.

|
 |
Civilian Aviation (Hangar Doors)

Kerr-McGee is a global energy and inorganic chemical
company based in Oklahoma City, OK. The company has
an existing hangar that required additional space for
fleet upgrades and future additions. The present hangar
three leaf steel sliding door allowed an overwhelming
infiltration of birds, dust, and air in the facility
(see photo1). Many steps were taken to alleviate the
problem, but non successful.
|

Photo 1, Existing Steel Rolling Hangar Door
(Click
on image to enlarge) |
| With
the planning of a new facility, the aviation director
not only wanted a space for the care and maintenance of
the aircraft, but also one that would eliminate the infiltration
issues in the existing hangar. |

Megadoor provided the customer with a single leaf, 90’
wide by 28’ high, hangar door in the new addition.
This door, along with addition steps to cover the walls
and ceiling, has limited the infiltration of air and
dust in the hangar to practically non-existent, and
the bird problems are no longer an issue (see photo
2). The Megadoor provides the tightest seal of any hangar
door available. The photos shown of the existing sliding
door clearly indicate the areas around the doors that
can be used by birds and other varmints to enter the
hangar. In photo 2, the light seen are from the lighting
and the windows in the personnel doors.

|

Photo 2, Megadoor
(Click
on image to enlarge) |
 |
Civilian
Aviation (FedEx Memphis)

Previous experience between Megadoor and this worldwide
organizations architect was certainly a plus.
This new maintenance facility needed to be constructed
on a very tight site and must accommodate at least two
MD11s and an Airbus, in Hangar 12 and B-727 Aircraft
in Hangar 11. And, aircraft needed to be positioned
without opening the entire hangar.
|
 |

Megadoors design architect and FSB Designers/Engineers
worked together to create this new facility by maximizing
the use of the available space. Hangar #11 and #12 were
constructed using the unique Megadoor swing-up
mullion system to open any individual bay or open
the entire hangar. The Megadoors were literally designed
into the structure and the need for sliding door pockets
was eliminated. The final design of this fast-paced
design resulted in considerable savings of space, construction
costs and time. The use of Megadoors also resulted in
an ongoing maintenance cost reduction for FedEx. Due
to the nature of the maintenance work load, 20-30 aircraft
pass through the doors on a typical weekend. The hangar
is used around the clock, 7 days a week.

|
 |
Civilian
Aviation (Celsius Aerotech)

This five-bay hangar was originally designed for a sliding
door which would have forced the user to either close
or open the entire hangar even if access to a single
bay was all that was needed. This blocked or exposed
every bay and affected work in all areas.
|
 |

A MEGADOOR, engineered in five sections to correspond
with each bay, created a better working environment
and greater operation flexibility by allowing the user
access to individual bays. This also provided more appropriate
ventilation for the structure while eliminating an unwanted
air draft. Additional storage space was created by installing
the MEGADOOR in front of the main truss and side storage
pockets, needed for the old sliding door, were eliminated.
As an investment, the reliable MEGADOOR has needed little
maintenance over 12 years of operation and even when
a tornado caused several million dollars in damages
to the airport in 2000, the MEGADOOR survived virtually
unscathed.

|
 |
| Megadoor
Hangar Doors for Airbus A380 |
The
new huge aircraft Airbus A380 requires new hangars to
be built. Megadoor has supplied hangar doors for two new
hangars designed particularly for A380.
The hangar for Qatar Airways at Doha Airport has a Megadoor
multiple door with 7 door leaves. The fabric colour is
translucent white for improved light transmission into
the hangar. The Megadoor has a width of 145 m. The new
GAMECO maintenance hangar at Guangzhou Baiyun International
Airport in China has three Megadoor multiple doors. Two
of the Megadoors are divided into 5 door leaves and one
into 7 door leaves. The widths of the three Megadoors
are 96, 144 and 95 m. The Megadoor solution with swing-up
mullions between each door leaf, gives an optimal opening
flexibility. |
 |
Qatar
Airways - Doha Airport
|
 |
| GAMECO |
 |
| Megadoor
Hangar Doors for Fabric Hangars |
Framed fabric structures can be used as permanent hangars,
temporary hangars or relocatable / portable hangars.
Megadoor has proven to be the ideal door solution for
framed fabric hangars. Megadoor is a vertical fabric
folding door with horizontal aluminium beams. The door
can be designed for almost any wind load and opening
size.
|
 |
 |
Mining
(Silo Doors)

Management of the Thunder Basin Mine in Wright, Wyoming
had been experiencing numerous problems with the doors
surrounding their 250' high storage and loading silos.
An enormous amount of dust, grit and grime is common
in and around these silos, necessitating a complete
wash-down of the entire enclosure at least twice daily.
And, in the extreme temperature and severe winds of
Wyoming, the need to wash the doors caused icing and
door activation problems.
|
 |

The MEGADOOR was already familiar to the Thunder Basin
Mine, since previous installations in other areas of
the mine had provided good results. Therefore, choosing
another MEGADOOR to solve the silo problem was a natural.
It's been two years now and everyone is quite pleased
with the result. The flexibility of the fabric
allows any ice accumulation to merely fall off after
the wash-down, and our maintenance has been reduced
tremendously. In addition, we receive great service
and an unprecedented guarantee, plus the simplicity
of design reduces the potential for failure. All in
all, we've been very satisfied with MEGADOOR,
says a mine representative.

|
 |
Mining
(Wash Bay Doors)

Management of the Thunder Basin Coal Company's Black Thunder
mining facility, located in Wright, Wyoming, recently
had a problem in their wash bay area. Faced with winter
weather conditions of 80 miles per hour winds and -40°F
temperatures, the doors at Thunder Basin needed to withstand
the harshest conditions. Added to the weather concerns,
these doors needed to be operational under dirty and grimy
conditions generally associated with a major open pit
mining facility. Typically, other door types are prone
to excessive downtime when subjected to these conditions.
The MEGADOOR is specifically designed to withstand the
most extreme environments including high wind loads and
other conditions. |
 |

MEGADOORS were installed in a series of 38'-8"
x 30' doors in the wash bay facility at Thunder Basin.
Because of the unique and simplistic design of the door,
maintenance and downtime costs were dramatically reduced
when compared to conventional doors.
The
Thunder Basin project was installed by Wasatch Door
Company of Salt Lake City, Utah, whose manager, Mike
O'Driscoll believes that with MEGADOOR the Black Thunder
Mine now has a permanent solution to their wash bay
door problems.

|
 |
Wabush
Mine (Labrador, Canada)

The average winter temperature in Labrador, Canada is
minus 20° to 25° , and even as low as minus
30°. Wabush Mine officials wanted to do everything
possible to provide tolerable working conditions for
their employees and take every possible measure to make
facility choices that back up such concern.
|
 |
As
the Labrador Mine grew the methods used to close the
interior of the mine from the elements became more difficult.
Originally, the mine used 65-ton trucks, then 170-ton,
and later 200-ton. As the trucks got larger the openings
on their Vehicle Maintenance Building had to be enlarged
in both width and height while the support columns limited
the size of the door opening to only 15 inches of clearance.
Openings of this size make it virtually impossible to
maintain any degree of comfort within the building.
Megadoors
were chosen over metal or rubber doors because they
operate consistently and could open and close at least
30 times each day as required by one of the service
bays. They could be mounted on the exterior of the building
with the drive inside to utilize every inch of space.
The low profile of the Megadoor facilitated an easier
fit and the windload capabilities assured smooth operation
even during high wind conditions. |

Wabush Mines installed four Megadoors only four inches
apart and discovered some additional benefits. The double
fabric stops the cold winds that other doors can't,
creating a warmer environment for employees, especially
those working close to the door. This design also reduces
the tremendous noise produced by the 2000 h.p. engines.
Before Megadoor, employees could not hear each other
talk because of the noise reverberation. The unexpected
sound deadening quality of the Megadoor is noticeable
enough to give the employees some much needed relief.
The Megadoor operates when damaged and can be repaired
without being removed since the chances of both fabric
layers being torn is slim.
"Wabush
Mine management could not be more pleased with their
new door installation, says A. J. MacLean, Wabush
Project Engineer responsible for the door installation.
Not only do they have a new bank of doors that perform
well above their requirements and expectations, but
they also have a much more satisfied group of employees
who have realized that their company has chosen the
right equipment for such extreme environments!

|
 |
Other
Industries (Syncrude Canada Ltd.)
Syncrude
Canada Ltd., located in the oil sands of Northern Alberta,
is the world's largest producer of light, sweet crude
oil from oil sands, and the largest single source of
oil in Canada.
|
 |

With the size and quantity of haul trucks increasing
substantially in recent years at Syncrude, shop facilities
have required modification to accommodate them. One of
the most significant changes is the increase in Shop &
Wash Bay door sizes from 8M wide to 12M wide, within the
physical constraints of the existing buildings. |

Syncrude Canada Ltd. explored various options, and
after their Engineering & Maintenance people visited
a similar application at the Thunder Basin Coal Mine
in Wright, Wyoming in 1997, the Megadoor was selected
for retrofit to an existing Heavy Duty Shop, and for
a new Wash Bay. According to Syncrude's Project Manager,
"Shop space for haul trucks was at a premium, so
the problem of taking up extra space on the sides and
above doorways associated with conventional doors was
an issue. The Megadoor, with its light weight &
minimal space requirements provided the solution for
these shops." After installing four 12M x 10M Megadoors
in 1997, four more were installed in 2000.

|
 |
Automotive
(Plant Rail Door)

This particular door is in the main rail car receiving
area of a large automotive plant and when the door is
damaged, production is interrupted. The existing rolling
steel door was often hit by the rail cars causing considerable
damage and costly repairs. In addition, the door would
bind when being opened or closed under the occasional
60-70 mph winds in the area. |
 |

The MEGADOOR SYSTEM 800 was selected by plant engineers
after several doors were evaluated. This particular
product was chosen because it generally works even when
damaged and it's easy to repair. Plus, it is operational
in winds up to 100 mph and is an excellent choice for
installation in a dusty, dirty environment. Since its
installation, the MEGADOOR has also been hit by a rail
car, but easily repaired with virtually no downtime.
The door has been in place for about three years now
and continues to perform beautifully. Needless to say,
everyone involved is delighted with the MEGADOOR.

|
 |